Costa Rica airport expands to meet projected long-term growth

By Sophia Klempner
Tico Times Staff | sklempner@ticotimes.net

Juan Santamaría International Airport's new operator announced this week the completion of several expansion works and plans to continue improving the airport's terminal and other facilities.

The operator, Aeris, is a conglomerate of Canada's Airport Development Corporation, the U.S.-based Houston Airport System Development Corporation and Brazil's Andrade Gutierrez Concessôes.

To date, Aeris has completed long-awaited works such as doubling the immigration lanes in the arrival area from 14 to 28, finishing the departures hall, and adding a new security area that doubles the capacity of the previous facility. The immigration area where exit documents are reviewed, has also been expanded.

The construction in the first phase also includes a diplomatic hall, a new boarding area, a new boarding ramp, a mechanical support building, completion of the new east terminal, and an electrical substation.

In an e-mail communication to The Tico Times, Aeris said, “For the July vacations, we have increased the number of check-in counters from 58 to 78, which will speed up check-ins.”

The expansion's second phase includes two additional boarding areas with ramps, a remote hall, and taxi ramps for two planes, and will be finished no later than Dec. 31. However, Aeris said they are “hoping to finish by the beginning of the 2010-2011 high season, somewhere between Oct. 15 and Nov. 15.”

Aeris estimated the cost of the work finished in April at $30 million, and that of the additional work to be completed by the end of this year at $10 million.

Two additional expansion phases are in final discussions and the plans for these will be submitted to the Civil Aviation Technical Council (CETAC) by Aug. 31, said Aeris.

Preliminary conclusions show that if all four planned expansion phases are completed, the airport will have the capacity to handle the increased demand and passengers from now until 2029, when an estimated 12 million passengers per year are expected. The projection is based on an annual estimated growth rate of 5.2 percent, said Aeris.

 
Comment on this article
First name *
Last name *
E-mail *
Country *
City *
Comment *
Max.: 1,800 characters How to add a comment

 

More Daily News

 
a
RETURN TO THE TOP OF PAGE

HOME | SUBSCRIBE | ADVERTISE | GUIDEBOOKS | BACK ISSUES | ARCHIVE SEARCH | CONTACT US | ABOUT US | NEWSSTANDS | LINKS | POLICIES